All projects

South Fly District

Gaima Project

A 6-in-1 classroom with a high-set house and two low-set moto houses.

Funder
Fly River Provincial Gov
Value
K3m

Photographs

  • Gaima Project — steel floor frames laid out on the cleared site, seen from the air
  • Gaima Project — a worker drilling a steel frame section
  • Gaima Project — floor frames assembled on the grass, seen from the air
  • Gaima Project — four workers fitting steel frame sections together
  • Gaima Project — the yellow two-storey building with solar panels on its roof
  • Gaima Project — the finished classroom and staff buildings, seen from the air

Scope of work

  • Feasibility: Define the need, test viability, secure funding and approvals.
  • Design and planning: Drawings, specs, schedule, permits.
  • Procurement: Tender, select contractors and suppliers, sign contracts.
  • Mobilization: Set up site, bring in people and equipment, kick off.
  • Construction: Build in phases while tracking cost, time, and quality.
  • Commissioning: Test systems against design.
  • Handover: Final inspections, transfer the asset, close accounts.
  • Defects liability: Fix defects during the warranty period (usually 12 months).

Other works

  • 1x High Set G202 House
  • 2x Low Set Moto House
  • 1x 4in1 Classroom